67th Avenue NE roadwork starts Aug. 12
Construction on 67th Avenue NE in Marysville, WA, begins on Aug. 12, focusing on improvements between Grove Street and 88th Street. The city’s contractor, Bayshore Construction, will replace pedestrian ADA ramps and overlay the roadway with new pavement. During the initial phase, the southbound lane will close for ADA ramp demolition, but one lane in each direction will remain open. In mid-September, grinding will shift to the center and northbound lanes, with additional closures for ramp work on 88th Street.
The paving phase is scheduled for the first week of October, anticipated to last 2-3 days. Construction is expected to conclude by late October, enhancing safety and accessibility. Residents should prepare for delays and consider alternate routes. Pedestrian access will remain open throughout the construction period.